US data centers are drawing electricity about ten times faster than the grid can grow. Many facilities may soon have to produce a large share of their own power outside the public network.
Howden, an insurance-focused consultancy, built this picture from data of the US Energy Information Administration and S&P Global. Since 2000, power fed to data campuses has risen 19% a year on average, while the grid has expanded its capacity by 2% a year. In 2025 data centers accounted for about 5% of US grid capacity, up from 0.1% in 2000, a fifty-fold increase.

Image: Dipartimento dell'Energia USA — https://www.energy.gov/policy/electricity-demand-growth-resource-hub
The problem is not only volume. Connections take years: for the largest and most power-constrained projects, Howden warns of delays of two to six years, which could mean $800 million to $2.4 billion in forgone revenue. Independent analyses point the same way: new loads are arriving faster than electrical infrastructure can follow.
A chart in Howden's report seems to show the two lines about to cross, but the scales differ sharply: 1,400 gigawatts for the grid, only 80 for data centers. Data centers taking over all of America's electricity is not an immediate risk.
Keeping data centers at 5% of grid capacity would nonetheless require around 110 gigawatts of behind-the-meter generation by 2030. Howden considers that unlikely and expects a mix of greater grid reliance, slower development at constrained sites and alternative supplies.
That last route explains the rush toward self-generation. The sources point to on-site natural gas as the most cited option, alongside renewables, batteries and nuclear. Howden notes that on-site generation brings new operational and financial exposure, as operators take on more direct responsibility for their energy infrastructure.
Much of this remains hard to see. A Telegraph investigation describes a "shadow grid" of new private plants, some running on fuel cells and others on portable gas turbines, often under confidentiality agreements.